Essential Maintenance on the A50 Junction 1 Roundabout, Donington

Essential Maintenance on the A50 Junction 1 Roundabout, Donington

The work involves resurfacing the carriageway, renewing road markings and replacing worn bridge joints.

The works will start on 8 January 2019 and we expect to finish on 18 January 2019. To minimise disruption we will work overnight, between the hours of 19.00 and 06.00, on week nights (Monday to Friday) only.

The work will be delivered in two phases; the northern half for the first week and the southern half for the second. To carry out this work safely we will need to close half of Junction 1 of the A50 over week nights for the duration of the scheme. During the closures we will put in place fully signed diversion routes.

I apologise in advance for any disruption this may cause you. Please note that all planned roadworks are subject to change due to weather conditions or unforeseen circumstances. We will do our very best to complete the work as quickly as possible, keeping disturbances and noise to a minimum.

Posted: Wed, 12 Dec 2018 09:36 by Chris Hills